Spectacular Girder Placing at Railway Bridge Lindwurmstrasse

Einhub an der Eisenbahnbrücke Lindwurmstraße

14. May 2025

Steel girders for new bridge superstructure

In the night from 12 to 13 May things got moving: at the replacement of railway bridge Lindwurmstrasse the first 14 of in total 26 rolled concrete girders (WiB) were placed – while railway traffic was maintained.

Each of the 34-metre-long steel girders weighs around 9.6 tonnes and was delivered directly to the construction site by heavy haulage transport – two girders per truck. Placing of the girders was a matter of millimetres: placing took around 30 minutes for each girder.

A large step for the bridge superstructure – and a great spectacle for everyone live on site.