Construction Site Update: New Rahmede Viaduct
11. October 2024
Firs milestones accomplished
In May 2023, during a spectacular undertaking, Rahmede viaduct had been demolished by controlled explosion. For almost one year, construction to erect the replacement have been in full swing. Currently, construction progress is clearly visible. The first piles have been completed, the subsequent ones continuously grow in height. The piles are concreted step by step using a so-called climbing formwork. The highest of the piles will reach a height of around 70 metres.
Construction of the superstructure has reached a first milestone as well: during the first launching phase, a part of the steel superstructure has reached the temporary pile. This procedure is implemented by incremental launching. After assembly of the individual steel segments, they are launched from the assembly yard over the piles towards the valley.
The new large-scale bridge is a steel-concrete composite structure and will be around 450 metres long, consisting of two parts. The first sub-structure is planned to be opened in mid-2026. Until then, a large part of the second sub-structure will be visible.
SSF Ingenieure has been contracted by Autobahn GmbH des Bundes in a joint venture together with Eberhardt Ingenieure and Schüssler-Plan for construction management, supervision and assembly supervision.