High-speed Railway Line from Wuhan to Guangzhou Passenger Dedicated Line
Consulting, examination and training of on-site supervision for engineering structures, earthworks, tunnel construction and superstructures, track construction, overhead-cable and signalling technology as well as production of prefabricated single-span girders 32 and 24 m system. Control of supervision of girder construction on site.
Several big bridges in the Pearl River delta as steel truss and cantilever bridges:
Mao Jia Bian Major Bridge, Kuangqu Major Bridge, Chechengjia Major Bridge
Bridge construction: 2 beam factories, 6 ‘Super Giant Bridges' (single-span girders with maximum length of 11 km), cast in-situ concrete continuous girder bridges max. 94 + 168 + 94 m, truss arch bridge with spans 99 + 242 + 99 m
Earthworks: 6 earthwork sections approx. 3 km long incl. Huadu Station
Tunnel construction: Jinshazhou tunnel (approx. 4.3 km long, inner-urban area, superficial, very difficult geology) and Da Song Ling Tunnel (approx. 200 m)